Project management is the application of knowledge, skills, tools, and techniques to project
activities in order to meet or exceed stakeholder needs and expectations from a project. Meeting or
exceeding stakeholder needs and expectations invariably involves balancing competing demands
among:
- Scope, time, cost, and quality.
- Stakeholders with differing needs and expectations.
- Identified requirements (needs) and unidentified requirements (expectations).
The term project management is sometimes used to describe an organizational approach to the
management of ongoing operations. This approach, more properly called management by projects,
treats many aspects of ongoing operations as projects in order to apply project management to
them. Although an understanding of project management is obviously critical to an organization
that is managing by projects.
Primavera project planning

1st week course
- Contractual start and finish date
- Contract value. Payments terms and conditions.
- Collect scope of work
- BOQ or FOT( form of tender)
- Contractual milestones if any
- List of drawings
- Actual Execution Plan or Strategy
- Preliminary schedule ( level 1 or level 2 schedule if any)
- Organization chart company and contractor and contact numbers/emails
- Available manpower & equipment status
- Create Project:
- Project ID: PRJ-XYZ1
- Project Nam : Office building with HVAC & Fire Fighting
- Set Planned Start (As per contract )
- Set Planned finish (As per contract )
- Create Calendar:
- Create customized calender for Engineer, Procurement and Construction
- Create any customized calendars as required ( commissioning, etc)
- Mark public holidays during project duration ( say for 2 years)
- Create WBS
- Better to create WBS as per format of (BOQ / Form of tender)
- Project milestones, General, Engineering, Procurement, Construction, pre-commissioning & commissioning and Handover.
- Under construction
- Civil works
- Sub Structure
- Super Structure
- Mechanical works
- Electrical & Instrumentation works
- Civil works
- Create Activities
- Then give duration ( Note: duration based on quantity of work)
- Set all activities duration type as physical
- Give logical relationship and as per actual execution plan
- Give mandatory constraint if any only ( Better to avoid constraint in normal practice)
2nd week Course
- Adjust LAGS then DURATIONS in order to match contractual start and finish date.
- Copy and paste activities in excel file
- Calculate activity cost from BOQ ( for this )
- Break down BOQ cost to WBS level
- Then WBS level to Activity level ( recommended to assign cost only to those which are mentioned in BOQ)
- Finally/eventually break down cost match with BOQ total cost
3rd week Course
- Assign activity cost in primavera schedule by creating dummy resource ( note: for dummy resource remove tick from “auto complete actual” from resource-detail tab)
- First assign trapezoidal cure then enter activity cost
- ENSURE TOTAL SUMMRY COST MATCH WITH CONTRACT COST.
4th week Course
- WHICH COMPLETES PROJECT BASE LINE SCHEDULE ( LEVEL 2 – LEVEL-3- LEVEL-4 )
- LEVEL4 DETAIL SCHDLE. ( note : Plz ensure all BOQ items should cover in schedule)
- Float should not more than 10% of project duration
- There should not be open ends.
- We have to use minimum lag